Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|c|c|c|c|c|} \hline\text { Activity } & \text { Slack } & \begin{array}{c} \text { Normal } \\ \text { Time } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Time } \end{array} & \begin{array}{c} \text { Normal } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash Cost } \\ \text { Per Week } \end{array} \\ \hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\ \hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\ \hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\ \hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\ \hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\ \hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\ \hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\ \hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\ \hline \end{array}   a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?  Activity  Slack  Normal  Time  Crash  Time  Normal  Cost  Crash  Cost  Crash Cost  Per Week  A 074$400$750B1129$1,000$2,200C076$800$1,100D065$600$1,000E086$1,200$2,200F932$800$1,000G932$500$650H043$400$600I065$900$1,300\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Activity } & \text { Slack } & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \begin{array}{c}\text { Normal } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash Cost } \\\text { Per Week }\end{array} \\\hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\\hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\\hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\\hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\\hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\\hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\\hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\\hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\\hline\end{array}
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?


Definitions:

Social Group Membership

The state of belonging to a group that shares common interests, purposes, or identities, influencing an individual's social identity and interactions.

Institutional Levels

Refers to the various stages or echelons of organization within institutions, often classified by hierarchy or complexity.

Culturally Competent

The ability to understand, communicate with, and effectively interact with people across cultures.

Administrative Processes

Procedures and operations related to the management and execution of office tasks, including documentation, scheduling, and organization.

Related Questions