The BOM for Product X is shown below, followed by a table of inventory data.The master production schedule quantity calls for the completion of 300 Xs in Week 7.The lead-time for production of X is 2 weeks and there are currently no units of X available. The BOM for Product X is shown below, followed by a table of inventory data.The master production schedule quantity calls for the completion of 300 Xs in Week 7.The lead-time for production of X is 2 weeks and there are currently no units of X available.     a.When and what quantity will be the planned order release for Item C? b.Determine the week and the quantity of the planned order release for Item D. The BOM for Product X is shown below, followed by a table of inventory data.The master production schedule quantity calls for the completion of 300 Xs in Week 7.The lead-time for production of X is 2 weeks and there are currently no units of X available.     a.When and what quantity will be the planned order release for Item C? b.Determine the week and the quantity of the planned order release for Item D.
a.When and what quantity will be the planned order release for Item C?
b.Determine the week and the quantity of the planned order release for Item D.


Definitions:

Related Questions