The BOM for Product X is shown below, followed by a table of inventory data.The master production schedule quantity calls for the completion of 300 Xs in Week 7.The lead-time for production of X is 2 weeks and there are currently no units of X available.
a.When and what quantity will be the planned order release for Item C?
b.Determine the week and the quantity of the planned order release for Item D.