Data regarding the activities for a project are presented below.The times are in weeks.The critical path for this project is A - D - H - I - J - K.
Data regarding the activities for a project are presented below.The times are in weeks.The critical path for this project is A - D - H - I - J - K.   a.Determine the standard deviation of the critical path. b.Determine the probability of completing the project in 38 weeks or less. c.What is the probability of completing the project in 32 weeks or less?
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?


Definitions:

Computers

Computers are electronic devices designed to execute operations and process data according to a set of instructions, used in a wide range of applications from personal to business.

Equipment

Tangible personal property used in operations, which may be considered a business asset and subject to depreciation for tax purposes.

Partnership Interest

An ownership stake in a partnership, representing a partner's share of the profits, losses, and capital.

Additional Contributions

Extra payments beyond the minimum required, often referring to retirement accounts or other savings plans.

Related Questions