A Company Has Used PERT for a Project and Wants

question 23

Essay

A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks.Three paths of concern in the PERT network have these mean durations and variances in weeks:
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks.Three paths of concern in the PERT network have these mean durations and variances in weeks:     a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?


Definitions:

Operant Conditioning

A method of learning that employs rewards and punishments for behavior.

Rational-emotive Therapy

A form of cognitive-behavioral therapy founded by Albert Ellis that helps individuals identify and change irrational beliefs that cause emotional distress.

Paradoxical Intervention

A therapeutic technique in which a therapist prescribes or suggests the continuation of the behavior symptomatic of the client's issue, often leading to change through resistance to the suggestion.

Social-learning Theory

A theory which posits that people learn new behaviors through observing and imitating others, alongside direct reinforcement.

Related Questions