A company wants to use PERT to manage a project.They have developed the following spreadsheet for the problem.If The Risk Solver Platform RSP) is used,what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
123456789 A Time Estimates Act A B C DE FG B a8235131MODEL C m10348252 D b144512473 E Random Number 0.730.190.560.940.350.090.59 F Activity Time 11.462.624.0610.722.033.872.09 G EST 011.46211.46215.52126.2426.2430.109 H EFT 11.46214.08115.52126.2428.27230.10932.202 I LST 0.0012.9011.4615.5228.0826.2430.11 J LFT 11.4615.5215.5226.2430.1130.1132.20 K SLACK 0.001.440.000.001.840.000.00 L ∗∗∗∗∗∗∗∗∗∗
Multi-national Group
An organization or collection of individuals from multiple countries who work together toward a common goal or are part of the same corporation operating in various nations.
Effective Listening
The skill of attentively hearing and understanding what someone else is communicating, critically assessing, and responding thoughtfully.
Communication Skill
Communication skill encompasses the ability to effectively convey and receive information, ideas, and emotions through verbal, non-verbal, written, and digital means.
Training
The act of providing individuals with the knowledge and skills needed to perform specific tasks or jobs effectively.