What Is the Late Start Time for Activity E Given

question 10

Multiple Choice

What is the late start time for Activity E given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5 B 7C8 A D7 A E4 B  F 8 C, D G9 E, F H7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & - \\\hline \text { B } & 7 & - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline E & 4 & \text { B } \\\hline \text { F } & 8 & \text { C, D } \\\hline G & 9 & \text { E, F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}


Definitions:

Objectives

Specific, measurable goals that are set to achieve a desired outcome or target.

Strategy

A plan of action designed to achieve a long-term or overall aim.

Listening

In marketing, actively monitoring and analyzing social media and other platforms to understand public perception and gather feedback about a brand or product.

Monitoring

The process of observing and tracking certain activities, behaviors, or information to gather insights or maintain control.

Related Questions