Project Test Bank Is Composed of Activities We Will Refer

question 82

Multiple Choice

Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?  Activity  Length  Predecessor A10B18A C 14AD20B,C\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline A & 10 & - \\\hline B & 18 & A \\\hline \text { C } & 14 & A \\\hline D & 20 & B , C \\\hline\end{array}


Definitions:

Work-Skills Assessment Tests

Evaluations designed to measure an individual's capabilities and competencies in relation to specific job roles or career paths.

Curse of Knowledge

This is a cognitive bias that occurs when an individual, communicating with others, unknowingly assumes that the others have the background to understand.

Mental Simulation

The cognitive process of imagining or visualizing hypothetical scenarios or outcomes in one’s mind.

Home Theater System

A collection of electronic components designed to recreate the experience of watching a movie in a theater at home, typically including a large screen, speakers, and various media players.

Related Questions