A Project Is Represented by the Activity Durations (Estimated at 90

question 57

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology?  Activity  Predecessor  Length  Activity  Predecessor  Length M8R12N8 SP14PM12ΓR,Q7QN10 V S, T11\begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \mathrm { M } & - & 8 & \mathrm { R } & - & 12 \\\hline \mathrm { N } & - & 8 & \mathrm {~S} & \mathrm { P } & 14 \\\hline \mathbb { P } & \mathbb { M } & 12 & \Gamma & \mathrm { R } , \mathrm { Q } & 7 \\\hline \mathrm { Q } & \mathbb { N } & 10 & \mathrm {~V} & \mathrm {~S} , \mathrm {~T} & 11 \\\hline\end{array}


Definitions:

Shelf Space

The area allocated for products in retail outlets, which can influence sales volume due to visibility and accessibility to consumers.

Economic Espionage

The act of secretly gathering proprietary or economically valuable information about the competition for commercial advantage.

Unethical Behavior

Unethical behavior refers to actions that go against moral principles and standards, often causing harm or disadvantaging others in the social or professional realm.

Competition

The presence of multiple companies or entities in the same marketplace, vying for the same customers or market share.

Related Questions