A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project.  Activity  Average  Worst-Case A1020B1525 C 2030D2535\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline A & 10 & 20 \\\hline B & 15 & 25 \\\hline \text { C } & 20 & 30 \\\hline D & 25 & 35 \\\hline\end{array}


Definitions:

Keystone Niche

A critical role that an organism plays in maintaining the structure and integrity of an ecosystem, often disproportionate to its abundance.

Specialist Niche

A narrowly defined role or position occupied by an organism or a business within an ecosystem or market, respectively, requiring specific adaptations or specialized skills.

Human Health

The overall condition of an individual's body or mind, especially in terms of the presence or absence of illnesses and impairments.

Sanitation Systems

Infrastructure and practices aimed at the safe and efficient collection, treatment, and disposal or reuse of human excreta and wastewater.

Related Questions