Consider the Portfolio of Projects Described in the Table A) A
B) B

question 15

Multiple Choice

Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The First in Line rule would begin work with project:  Resource  Resource  Resource  Project  Date Rec’d  Date Due 123 A  Apr 2006  Oct 2006 125200100 B  Feb 2006  Sep 2006 200350400 C  Mar 2006  Alg 2006 100650200 Tan 2006  Nov 2006 150250350\begin{array} { | l | l | l | l | l | l | } \hline & & & \text { Resource } & \text { Resource } & { \text { Resource } } \\\text { Project } & \text { Date Rec'd } & \text { Date Due } & 1 & 2 & 3 \\\hline \text { A } & \text { Apr 2006 } & \text { Oct 2006 } & 125 & 200 & 100 \\\hline \text { B } & \text { Feb 2006 } & \text { Sep 2006 } & 200 & 350 & 400 \\\hline \text { C } & \text { Mar 2006 } & \text { Alg 2006 } & 100 & 650 & 200 \\\hline & \text { Tan 2006 } & \text { Nov 2006 } & 150 & 250 & 350 \\\hline\end{array}