What Is the Cost Variance of Project Makeready Based on the Data

question 28

Multiple Choice

What is the cost variance of Project Makeready based on the data in the earned value table shown below? What is the cost variance of Project Makeready based on the data in the earned value table shown below?   A)  -$1,896 B)  -$1,096 C)  -$800 D)  -$406