Use This Earned Schedule Table to Determine the Schedule Performance

question 29

Multiple Choice

Use this earned schedule table to determine the schedule performance index (t) for this project at the end of Month 6.  Month 1 Month 2 Month 3 Month 4  Month 5 Month 6 Month 7PV($) $125$275$500$875$1,485$2,325$2,670 EV ($)  $50$120$255$420$715$865$0\begin{array}{|l|l|l|l|l|l|l|l} & \text { Month } 1 & \text { Month } 2 & \text { Month } 3 & \text { Month 4 } & \text { Month } 5 & \text { Month } 6 & \text { Month } 7 \\\hline \mathbb{P V}(\$) & \$ 125 & \$ 275 & \$ 500 & \$ 875 & \$ 1,485 & \$ 2,325 & \$ 2,670 \\\hline \text { EV (\$) } & \$ 50 & \$ 120 & \$ 255 & \$ 420 & \$ 715 & \$ 865 & \$ 0 \\\hline\end{array}


Definitions:

Supply Management

The process of identifying, acquiring, and managing the resources and suppliers needed by an organization to perform its operations effectively.

Decentralized Purchasing Structure

An organizational framework where purchasing decisions are made independently across different departments or locations, rather than being centralized.

Centralization

The organizational structure decision to concentrate decision-making authority and control at higher levels of management.

Supply Policies

Guidelines and rules set by an organization to govern its procurement activities and relationships with suppliers.

Related Questions