A Project Is Estimated to Cost $248,400 and Provide Annual

question 78

Essay

A project is estimated to cost $248,400 and provide annual cash flows of $50,000 for 8 years.Determine the internal rate of return for this project,using the following present value of an annuity table.
A project is estimated to cost $248,400 and provide annual cash flows of $50,000 for 8 years.Determine the internal rate of return for this project,using the following present value of an annuity table.