A Project Consists of the Following Activities

question 16

Multiple Choice

A project consists of the following activities:
A project consists of the following activities:    Table 9.1 -Using Table 9.1,the earliest start time for activity F is A) 30 weeks. B) 20 weeks. C) 14 weeks. D) 13 weeks.
Table 9.1
-Using Table 9.1,the earliest start time for activity F is