The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the expected time to complete activity A is A) 5.00 weeks. B) 7.33 weeks. C) 7.67 weeks. D) 8.00 weeks.
Table 9.2
-Using Table 9.2,the expected time to complete activity A is


Definitions:

Transductive Reasoning

Reasoning from the specific to the specific. (In deductive reasoning, one reasons from the general to the specific; in inductive reasoning, one reasons from the specific to the general.)

Memory

The processes by which we store and retrieve information.

Egocentrism

A cognitive trait where an individual is unable to understand or assume any perspective other than their own.

One-dimensional Thinking

A thinking process that is superficial and lacks depth, often focusing on a single aspect of a situation.

Related Questions