The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

question 68

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the expected time to complete activity A is A) 5.00 weeks. B) 7.33 weeks. C) 7.67 weeks. D) 8.00 weeks.
Table 9.2
-Using Table 9.2,the expected time to complete activity A is


Definitions:

Retained Earnings Account

An equity account that represents the accumulated profits of a company that have not been distributed to shareholders as dividends.

Income Statement Account

An income statement account is a financial account that reflects income, expenses, gains, and losses over a period, used to calculate net income.

Stock Dividend

A distribution of additional shares of a company to its shareholders instead of paying cash dividends, often used to conserve cash while still rewarding investors.

Par Value

The nominal or face value of a bond, stock, or coupon as stated by the issuer, which often bears no relation to its market value.

Related Questions