A Project Consists of the Following Four Activities with Activity

question 69

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:     Table 9.3 -Using Table 9.3,the critical path for this project is A) A-B-C. B) A-C-D. C) A-B-D. D) A-B-C-D.
Table 9.3
-Using Table 9.3,the critical path for this project is