The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,how much slack is associated with activity C? A) 0 weeks. B) 4.50 weeks. C) 12.67 weeks. D) 31.00 weeks.
Table 9.2
-Using Table 9.2,how much slack is associated with activity C?


Definitions:

Dictyostelium Discoides

Dictyostelium Discoides is a species of slime mold that is often used in research as a model organism for cellular processes.

Eukaryote

An organism whose cells contain a nucleus enclosed within membranes, distinct from prokaryotes, which lack such a nucleus.

Non-breeding Individuals

Organisms that are not currently involved in producing offspring, either due to life stage, season, or other biological or environmental factors.

Related Questions