If the Following Jobs Are Sequenced According to the SPT

question 2

Multiple Choice

If the following jobs are sequenced according to the SPT rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)
If the following jobs are sequenced according to the SPT rule then the mean tardiness (in days) for all jobs is (assume zero for today's date)    A) 16 days. B) 13 days. C) 5.2 days. D) 3.2 days