Consider a project having the following ten activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 1 5 9
B A 6 6 6
C A 3 5 9
D A 2 4 6
E B, C 4 4 4
F D 4 7 8
G E 2 2 8
H E, F 7 8 9
I F 4 6 9
J G, H, I 3 5 7
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 30 weeks?


Definitions:

Interpersonal

Relating to or involving relationships or communication between people.

Cohort Effects

Phenomena where the characteristics of a particular group of people born in the same period affect research outcomes due to shared historical and social experiences.

Great Depression

A severe worldwide economic downturn that took place during the 1930s, characterized by widespread unemployment, poverty, and deflation.

Maturity Principle

The idea that traits associated with effective functioning increase with age.

Related Questions