Scenario 8.1 - Gang Aft Agley
Gang Aft Agley,a manufacturing company,faces the aggregate planning problem shown in the table below.Cost of regular production is $5 per unit,the cost of producing the same unit on overtime is $7.50,the cost of subcontracting is $9 per unit,and the cost of carrying a unit in inventory from one month to the next is $2.
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window.The plant capacity is 600 units per month produced using two shifts,regardless of the number of days in a month.By policy,management wants to avoid stockouts.
-Use the information from Scenario 8.1 to determine the number of decision variables in this scenario.
Standard Costs
Predetermined costs assigned to goods and services, used as a benchmark for evaluating actual production costs.
Efficiency
The degree to which a process uses resources optimally to achieve a desired outcome.
Standards
Established norms or criteria in various fields that act as a basis for comparison or compliance.
Performance Goals
Specific objectives set for employees or departments, aimed at improving productivity and measuring success through quantifiable benchmarks.
Q1: As the response time desired by the
Q7: Supply chain network design decisions include the
Q8: All inventory between a given stage in
Q9: When a firm places orders in lot
Q21: Demand is forecast for the next five
Q39: How many units are produced using overtime
Q47: A manufacturer of lawn care equipment has
Q80: Use exponential smoothing to forecast the demand
Q90: As the safety inventory is increased,<br>A)fill rate
Q91: Where does distribution occur in the supply