Examlex

Solved

If the Project Manager Controls When and What People Do

question 35

Multiple Choice

If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used,the __________ organizational form is probably being used.


Definitions:

3-sigma Control Limits

Statistical boundaries set at three standard deviations from the mean in a control chart, used to determine the variability of a process and identify potential outliers or trends.

Standard Deviation

A measure of the amount of variation or dispersion of a set of values.

Sampling Distribution

Sampling distribution is a statistical term describing the distribution of sample means or proportions over repeated sampling from the same population.

Standard Deviation

A statistical measure of the dispersion or variability within a dataset, indicating how spread out the numbers are from the average.