___________ Is Described as Follows: CPM Is Usually Used for Projects

question 21

Multiple Choice

___________ is described as follows: CPM is usually used for projects with predictable task times. CPM is a deterministic model that does not take into account variation in the completion time, so only one number is used for an activity's time estimate.