During the Most Recent Month at Coggan Corporation,queue Time Was

question 49

Essay

During the most recent month at Coggan Corporation,queue time was 5.3 days,inspection time was 0.5 day,process time was 1.9 days,wait time was 4.5 days,and move time was 0.5 day.
Required:
a.Compute the throughput time.
b.Compute the manufacturing cycle efficiency (MCE).
c.What percentage of the production time is spent in non-value-added activities?
d.Compute the delivery cycle time.


Definitions:

Unit Amount

A specific quantity or measure of something, often used to standardize measurements or compare values.

Total Amount

The aggregate sum or the entirety of a particular set of numbers, values, or transactions, representing the overall total.

Materials Price Variance

The difference between the actual cost of materials and the expected (or standard) cost, used in budgeting and cost management.

Materials Quantity Variance

Materials Quantity Variance is the difference between the actual amount of materials used in production and the expected (or standard) amount, affecting cost management.

Related Questions