Given the Order-Requirement Digraph Below (With Time Given in Minutes)

question 62

Multiple Choice

Given the order-requirement digraph below (with time given in minutes) , apply the critical-path scheduling algorithm to construct a schedule using two processors. How much time does the resulting schedule require? Given the order-requirement digraph below (with time given in minutes) , apply the critical-path scheduling algorithm to construct a schedule using two processors. How much time does the resulting schedule require?   A)  14 minutes B)  15 minutes C)  16 minutes D)  18 minutes


Definitions:

Essential Attributes

Fundamental qualities or characteristics that define the nature of something, without which it would not be what it is.

Genus

A category that encompasses a collection of entities with shared traits, frequently employed in the taxonomy of biology to indicate a level higher than species but lower than family.

Differentia

The trait or characteristic that distinguishes one thing from another, especially within classification.

Circular

Referring to a shape or movement that is round in form and has no beginning or end point.

Related Questions