In the 15 years ending June 2010, most active portfolio managers failed to beat the market.


Definitions:

PERT Times

An abbreviation for Program Evaluation and Review Technique, specifically referring to the estimated durations for tasks involved in project planning.

Optimistic

Having a positive or hopeful outlook on situations, believing that the most favorable outcomes are likely to occur.

Pessimistic

Having a tendency to see the worst aspect of things or believe that the worst will happen.

Gantt Charts

Gantt charts are visual project management tools used to schedule tasks within a project, showing start and end dates, as well as dependencies between tasks.