Total Slack Can Be Calculated as the Difference Between the Latest

question 62

True/False

Total slack can be calculated as the difference between the latest start (LS) and earliest start (ES), or by the difference between the latest finish (LF) and earliest finish (EF).


Definitions:

Force Field Analysis

A method used in change management to identify and evaluate the forces for and against a change, facilitating decision-making and strategy development.

Plan for the Change

A strategy or set of steps designed to successfully implement new policies, practices, or systems.

Logical Incrementalism Model

is a strategic management approach suggesting that strategies should evolve gradually through a series of small, achievable steps, rather than through drastic, major changes.