Examlex

Solved

Table 32
Time (Days) -Using Table 3

question 76

Multiple Choice

Table 3.2
Time (days)
 Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 246 B 147 C  A 222 D  B 1710 E  D 246 F  E 123 G  C 3417 H  D, G 3711 I  D 8910 J  F,H 456 K  I 111\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & \cdots & 2 & 4 & 6 \\\text { B } & \cdots & 1 & 4 & 7 \\\text { C } & \text { A } & 2 & 2 & 2 \\\text { D } & \text { B } & 1 & 7 & 10 \\\text { E } & \text { D } & 2 & 4 & 6 \\\text { F } & \text { E } & 1 & 2 & 3 \\\text { G } & \text { C } & 3 & 4 & 17 \\\text { H } & \text { D, G } & 3 & 7 & 11 \\\text { I } & \text { D } & 8 & 9 & 10 \\\text { J } & \text { F,H } & 4 & 5 & 6 \\\text { K } & \text { I } & 1 & 1 & 1 \\\hline\end{array}
-Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.


Definitions:

Gardenburger Makers

Companies or entities involved in the production of Gardenburger, a brand of meatless burgers.

Normal Good

A type of good for which demand increases as the income of the consumer increases and decreases as the income of the consumer decreases, all else being constant.

Income

Money received, especially on a regular basis, for work or through investments, constituting the financial gain derived from labor, capital, or other sources.

Hamburgers

In an economic context, refers to a commonly cited example of a product in studies of competition, pricing, and consumer choice.

Related Questions