You are responsible for managing a project with the following activities
(times are given in weeks) .
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array}
-Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase?


Definitions:

Denial

A defense mechanism where a person refuses to accept reality or facts, acting as if a painful event, thought, or feeling did not exist.

Defense Mechanisms

Protective strategies unconsciously applied to avoid the discomfort arising from thoughts or feelings that are not acceptable.

Id Impulses

The instinctive and primitive behaviors and urges that are derived from the id part of the psyche, according to Freudian theory.

Related Questions