Refer to the table below to answer the question(s) that follow:
                         Activity                                 Times (weeks) Activity  Predecessor  Optimistic  Most Likely  Pessimi  A 91521 B 132123 C  A 6918 D  A 233547 E  B 192627 F  C 232941 G  D,E 142026 H  F,G 258~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\\begin{array}{c}\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\\hline \text { A } & --- & 9 & 15 & 21 \\\text { B } & --- & 13 & 21 & 23 \\\text { C } & \text { A } & 6 & 9 & 18 \\\text { D } & \text { A } & 23 & 35 & 47 \\\text { E } & \text { B } & 19 & 26 & 27 \\\text { F } & \text { C } & 23 & 29 & 41 \\\text { G } & \text { D,E } & 14 & 20 & 26 \\\text { H } & \text { F,G } & 2 & 5 & 8\end{array}
-What is the probability that the critical path for this project will be completed within 75 weeks?


Definitions:

Break-even

The point at which total costs and total revenues are equal, meaning that there is no net loss or gain.

Unit Sales

The quantity of product units sold by a business during a specific period, often used to gauge performance.

Selling Price

The amount a buyer pays to acquire a product or service, potentially including discounts, allowances, and added taxes.

Fixed Expense

Costs that do not change with the level of production or business activity, such as rent or salaries.

Related Questions