Refer to the Table Below to Answer the Question(s) That

question 72

Short Answer

Refer to the table below to answer the question(s) that follow:
                         Activity                                 Times (weeks) Activity  Predecessor  Optimistic  Most Likely  Pessimi  A 91521 B 132123 C  A 6918 D  A 233547 E  B 192627 F  C 232941 G  D,E 142026 H  F,G 258~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\\begin{array}{c}\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\\hline \text { A } & --- & 9 & 15 & 21 \\\text { B } & --- & 13 & 21 & 23 \\\text { C } & \text { A } & 6 & 9 & 18 \\\text { D } & \text { A } & 23 & 35 & 47 \\\text { E } & \text { B } & 19 & 26 & 27 \\\text { F } & \text { C } & 23 & 29 & 41 \\\text { G } & \text { D,E } & 14 & 20 & 26 \\\text { H } & \text { F,G } & 2 & 5 & 8\end{array}
-Within what amount of time (in weeks) is there a 90% probability that the critical path for this project will be completed?


Definitions:

Prizes

Prizes are awards or rewards given for a specific achievement, often used as a form of recognition or incentive in various fields.

Interest Rate

The cost of borrowing money, expressed as a percentage of the amount borrowed per unit of time.

Current Amount

The present value or total of a particular financial metric, often used in contrast with past or future amounts.

Stock Variable

A variable measured at a specific point in time, representing a quantity that exists or is accumulated, such as a country's debt or a company's inventory.

Related Questions