Given the Following Information for a Project, Draw the AON

question 21

Essay

Given the following information for a project, draw the AON (Activity-On-Node) project network.
 Activity  Immediate  Processor  Activity Time  (days)  A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}


Definitions:

Present Value Factor

A multiplier used to determine the present value of a future cash flow, taking into account a specific discount rate.

Annuity

An investment vehicle providing a constant flow of payments to the owner, usually utilised as a source of income for retired people.

Net Cash Flow

The variance between the cash coming into and going out of a business within a set timeframe.

Compound Interest

The calculation of interest on the initial principal, which also includes all of the accumulated interest from previous periods on a deposit or loan.

Related Questions