Consider the Following Project -What Is the Latest Possible Time That Activity E Can

question 48

Multiple Choice

Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-What is the latest possible time that Activity E can be started without delaying the completion of the project?


Definitions:

Compensation System

The combination of salary, wages, and benefits that an employer provides to employees in exchange for their work.

Flexible Work Schedules

Work arrangements that allow employees to vary their arrival and departure times, as well as work locations, to accommodate personal needs and improve work-life balance.

Compensation System

A structure designed by organizations to determine how employees are remunerated for their contributions.

Intrinsic Rewards

The personal satisfaction and enjoyment derived from performing a job or completing a task, arising from within the individual rather than from external factors.

Related Questions