Consider the Following Project -What Is the Latest Time That Activity B Can Start

question 70

Multiple Choice

Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-What is the latest time that activity B can start without delaying the project?


Definitions:

National Debt

The total amount of money that a country's government has borrowed, typically from external or internal sources, to fund its operations and initiatives.

Recessionary Gap

The situation where an economy's real GDP is lower than its potential GDP, indicating underutilized resources and unemployment.

Equilibrium GDP

The level of Gross Domestic Product where aggregate supply equals aggregate demand, and the economy is in a state of balance.

Multiplier

The factor by which a change in investment, government spending, or other forms of economic activity is magnified in the overall economy.

Related Questions