A PERT/CPM Activity Has an Optimistic Time Estimate of 4

question 36

Multiple Choice

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is: