A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 100x1 + 120x2 + 90x3 + 135x4
s.t. 150x1 + 200x2 + 225x3 + 175x4 ? 500 {Constraint 1}
X1 + x2 + x3 + x4 ? 2 {Constraint 2}
X2 + x4 ? 1 {Constraint 3}
X2 + x3 ? 1 {Constraint 4}
X1 = x4 {Constraint 5}
Which of the constraints ensures that at least two of the potential projects will be selected?
Special Item
Unusual or infrequent gains or losses not classified as extraordinary but significantly important to understand a company's financial health.
Asset Increase
An increase in the total value of assets owned by a company, which can occur due to acquisitions, improvements, or valuation increases.
Corresponding Decrease
A decrease in one variable or metric that occurs in response to an increase in another variable.
Liability
A financial obligation or debt that an entity is required to pay to another entity.
Q4: The discovery of the simplex method in
Q18: A manager has determined that a potential
Q31: Which of the following would not be
Q41: Note: This problem requires the use
Q47: You have decided to start a vending
Q54: Professor Z needs to allocate time
Q69: A freelance writer must choose how to
Q70: Simulation models are fairly easy to use
Q72: Given the following 2 constraints, which solution
Q84: After the data is collected the next