A Production Line Is to Be Designed for a Job

question 25

Multiple Choice

A production line is to be designed for a job with four tasks.The task times are 2.4 minutes,1.4 minutes,0.9 minutes,and 1.7 minutes.After line balancing,the largest possible assigned cycle time is ________ minutes,and the smallest possible assigned cycle time is ________ minutes.