An Assembly Line with 11 Tasks Is to Be Balanced

question 15

Essay

An assembly line with 11 tasks is to be balanced.The longest task is 2.4 minutes,the shortest task is 0.4 minutes,and the sum of the task times is 18 minutes.The line will operate for 600 minutes per day.
(a)Determine the minimum and maximum cycle times.
(b)What range of output is theoretically possible for the line?
(c)What is the minimum number of stations needed if the maximum output rate is to be sought?
(d)What cycle time will provide an output rate of 200 units per day?

Recognize and understand the concept of overlapping categories in frequency distributions.
Interpret data tables to find specific statistical information.
Identify and correct common spelling errors.
Develop an understanding of the correct spelling of frequently used words.

Definitions:

Financial Statements

Formal records of the financial activities and condition of a business, entity, or individual, including balance sheet, income statement, and cash flow statement.

Acquisition Differential

The gap between what a company is bought for and the net market value of its recognizable assets and liabilities.

Joint Venture

A business entity created by two or more parties, generally characterized by shared ownership, shared returns and risks, and shared governance.

Retained Earnings

Accumulated net profits of a company not distributed as dividends but reinvested in the business or kept as a reserve.

Related Questions