Three Critical Path Activities Are Candidates for Crashing on a CPM

question 120

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost? a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?


Definitions:

Concentric Contractions

A type of muscle contraction in which the muscle shortens while generating force.

Muscle Tension

The force generated by the contraction of muscle fibers, often in response to external stimuli or neural activation.

Isometric Contractions

Muscle contractions where the muscle exerts force without changing length, used for stabilization and posture.

Tetanus Of Muscles

A condition characterized by prolonged contraction of skeletal muscle fibers caused by potent toxins produced by the bacteria Clostridium tetani.

Related Questions