A Project Consists of the Following Activities

question 58

Multiple Choice

A project consists of the following activities:
A project consists of the following activities:    Table XX -Using Table XX,the time complete the entire project is A) 20 weeks. B) 30 weeks. C) 36 weeks. D) 39 weeks. Table XX
-Using Table XX,the time complete the entire project is