The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

question 22

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the earliest finish time for activity C is A) 5.00 weeks. B) 8.17 weeks. C) 9.50 weeks. D) 12.67 weeks. Table ZZ
-Using Table ZZ,the earliest finish time for activity C is