Two Critical Path Activities Are Candidates for Crashing on a CPM

question 45

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or Two should be crashed;$1,400


Definitions:

Customers

Individuals or organizations that purchase goods or services from a business, determining its success through their satisfaction and loyalty.

Technology

The application of scientific knowledge for practical purposes, particularly in industry and everyday life.

Account Control

The process of managing and overseeing a customer account to ensure satisfaction, retention, and profitability.

Related Questions