A project has the following activities,durations,costs,and precedence relationships:
Activity A B C D E F G H I Present Duration (Weeks) 1015102015171297 Accelerated Duration (Weeks) 91361810151086 Immediate Predecessor Activities −− A A C B B D,F G,H Present Cost $11,00020,0009,00025,00020,00020,00015,00012,00010,000 Accelerated Cost $15,00025,00020,00030,00035,00030,00025,00018,00015,000 Develop a cost-time trade-off analysis.Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost.Determine each step's cost and the duration of the project.