Case 8.1 the Edward James Toy Company Uses a Kanban System to System

question 78

Multiple Choice

Case 8.1
The Edward James Toy Company uses a Kanban system to make plastic wheels that are a component of several toys.The waiting time for a container of the wheels during production is 0.25 day;average processing time is 0.15 day per container.Each container holds 200 wheels.The company uses 2000 wheels a day in the production of its products.
-Use the information in Case 8.1.Using a policy variable of 5%,calculate the number of Kanban containers needed for the wheels.


Definitions:

Hard Enough

A phrase typically used to describe a situation or task that requires a significant degree of effort or determination to overcome.

Responsible Student

A student who consistently demonstrates reliability, accountability, and a commitment to fulfilling their academic and social responsibilities.

Facebook And Instagram

Social media platforms that allow users to share content, communicate, and connect with others online.

Fundamental Attribution Error

The tendency to overestimate the influence of personality and underestimate the influence of situational factors when evaluating others' behaviors.

Related Questions