Table 2.6 -Using Table 2.6,how Many Days Can Activity C Be Delayed

question 64

Multiple Choice

Table 2.6
Table 2.6    -Using Table 2.6,how many days can activity C be delayed without changing the whole project's earliest completion time? A) 0 days B) 2 days C) 5 days D) 7 days
-Using Table 2.6,how many days can activity C be delayed without changing the whole project's earliest completion time?