Table 7.3 -Using Table 7.3, Which Activity Is on the Critical Path

question 80

Multiple Choice

Table 7.3
Table 7.3    -Using Table 7.3, which activity is on the critical path? A)  Activity D B)  Activity F C)  Activity G D)  Activity K
-Using Table 7.3, which activity is on the critical path?