A Firm Is Planning to Set Up an Assembly Line

question 149

Essay

A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks which precede each task are:
A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks which precede each task are:    a.Draw a network diagram of precedence relationships. b.Compute the required cycle time per unit in minutes. c.Compute the theoretical minimum number of workstations required to produce 40 units per hour. d.Balance this line using longest processing time. e.What is the efficiency of the line obtained in part d? a.Draw a network diagram of precedence relationships.
b.Compute the required cycle time per unit in minutes.
c.Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d.Balance this line using longest processing time.
e.What is the efficiency of the line obtained in part d?


Definitions:

Adolescent Girls

Female individuals who are in the stage of development between childhood and adulthood, typically between the ages of 10 and 19.

Identity Moratorium

A stage in Erik Erikson’s theory of psychosocial development where individuals are exploring various commitments and are yet to make clear choices about aspects of their identity.

Explored

Investigated or examined for the purpose of discovery and learning more about a subject.

Future

The time or period that is to come which has not occurred yet.

Related Questions