An assembly line with 11 tasks is to be balanced.The longest task is 2.4 minutes,the shortest task is 0.4 minutes,and the sum of the task times is 18 minutes.The line will operate for 600 minutes per day.
(a)Determine the minimum and maximum cycle times.
(b)What range of output is theoretically possible for the line?
(c)What is the minimum number of stations needed if the maximum output rate is to be sought?
(d)What cycle time will provide an output rate of 200 units per day?
Unit Contribution Margin
The difference between the selling price per unit and the variable cost per unit of a product, indicating how much each unit sold contributes to covering fixed costs and generating profit.
Break-even
The situation in which complete costs equate to total revenues, achieving a break-even point with no gains or losses.
Unit Sales
The number of individual units sold by a company during a specific period.
Degree of Operating Leverage
A measure of how sensitive a company's operating income is to a change in sales, indicating the extent to which fixed costs are used in the production process.
Q3: Which of the following is not true
Q13: What does it mean to have a
Q16: A toy manufacturer has three different mechanisms
Q56: Internal failure costs are associated with scrap,rework,and
Q57: Solving a load-distance problem for a process-oriented
Q59: Identify five examples of technology's impact on
Q62: The transportation method,when applied to location analysis<br>A)minimizes
Q85: In assembly line balancing,the theoretical minimum number
Q104: Identify the 10 determinants of service quality.Describe
Q117: In what specific areas does the layout