A company is trying to balance production between 3 workstations on an assembly line. Currently there are 5 tasks that need to be performed. These tasks, ABCDE, have required times of 2 minutes, 4 minutes, 1 minutes, 3 minutes, and 10 minutes respectively. The assembly line needs to produce 40 units per day to meet demand and can work for up to 8 hours each day.
A. What is the required cycle time?
B. What is the theoretical minimum # of workstations?
C. Assign the tasks according to shortest task time.
D. Is there a better way to divide the work than in Part C?
Gather A Crowd
The act of assembling a group of people in a specific location for a purpose, such as a meeting, performance, or demonstration.
Task Performance
The execution or accomplishment of a specific work-related activity or assigned task.
Simple Task
An activity or assignment that is straightforward and easy to accomplish, requiring minimal cognitive effort or complexity.
Deindividuation
A psychological state characterized by a loss of self-awareness and individual accountability, often occurring in group settings.
Q7: A location decision for an appliance manufacturer
Q17: A(n)_ queuing system is one in which
Q25: A waiting line meeting the M/M/1 assumptions
Q38: Of the several determinants of service quality,access
Q49: A linear programming problem contains a restriction
Q53: Why is equipment utilization in process-focused service
Q63: The typical goal used when developing a
Q69: The objective of a linear programming problem
Q101: What is it called when competing companies
Q125: Which of the following workers is the