A Simple CPM Network Has Three Activities,D,E,and F

question 72

Multiple Choice

A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.